1)
What is the difference between planned independent requirement consumption and planned independent requirement reduction ?
Not Required.
2)
Which consumption parameters (Consumption mode/consumption period) are taken into account?
Consumption mode is 2
forward consumtion day 60 days
backward consumption day 30 days
pir date week 49 (14/12/2014)
Salesorder requirment date (02/12/2014)
but still it not showing in Md73 report.
3)
Where can I check whether a planned independent requirement is consumed or against which requirements it is consumed?
Not Required.(becoz i am checking the same in MD73 only)
4)
Why is a change to the strategy group or a consumption-relevant change in Customizing ineffective?
I have not done any changes.
5)
Which settings are required to consume calls for stock transfers with planned independent requirements
Transaction OMP6 we are using requirment class as 103 indicator as 1.
A consumption with planned independent requirements of a planning material is not possible.
but i am using planned independent requirements of a planning material 90% cases its happening perfectly we have configured the strategy type.
6)
How I can flexibly define against which MRP elements planned independent requirements are consumed?
Not Required.
7)
The availability check against planned independent requirement returns an unexpected result. What has to be checked?
Not Required.
8)
Why are monthly or weekly requirements not consumed even though the assignment requirement is in the same period?
We are doing weekly planning so 90% cases its working fine . so i think there would not be any problem.
9)
I am using several active planned independent requirement items. Can I control the order in which they are consumed?
Becoz i am using differnt plann number.