Re: Exception error message in MD04 - opening date in past

$
0
0

Hello Paulina,

 

When you run MRP with Scheduling 2 (Lead Time Scheduling and Capacity Planning), the production dates will be determined using your routing. When you run the MRP with scheduling 1 (Determination of Basic Dates for Planned Orders) the dates will be determined based on the In-house production time setup in the material..

 

The costing run will consider the rounting. The in-house production is only relevant for the planned orders:

The system requires the in-house production time to determine the planned dates for planned orders in materials

planning.

Kind regards,

Mariano