Hi Lakshimipathai,
Thanks for your reply. We have four level of production, in that first top two level in MTO and next two with MTS. If marketing person makes some changes in sales order then in next MRP run the changes will be taken place and always there is a communication gap between production and marketing. Due to that unnecessary stock is getting pilled up / delay is happening. So i was try to automatic update of customer delivery date to schedule lines. i could not able to get the settings.
We have developed a Z screen which will be used to update schedule line dates by planning person. After creating SO a mail will be triggered to planning person and planning person by looking capacity they will update the date ans same will be updated in schedule lines.
Anyway thanks for your reply
Regards / US